Switchgear pre-installation inspection
Pastikan equipment certificate meet area classification requirement
Remove temporary weather proofing, transport packing, and silica gel drying agent from switchgear, Cek cleanliness di dalam switchgear, specially for insulator
Compare switchgear equipment meets equipment schedule, specially rating and any circuit changes
Pastikan equipment meets spec, including weather, dust and vermin proofing
Switchgear post-installation inspection
Check switchboard assy for alignment, level, tighteness foundation bolts and fixing in general
Pastikan all panel doors and gland plate are bonded to switchboard structure
Pastikan all equipment installed in switch board are in good conditions
Inspect busbar joint
Pastikan all insulators are clean, free from damage and not subjected to undue mechanical stress
Cek all items corresponded to material list
Cek all damages items
Clearence phase to phase and phase to earth are acordance with spec
Section clearances are satisfactory
Earthing connection connected to all necessary points and clear of other metal
Earthing connection tight, greased and thinned as required. Inspect the switchboard earth bar and earth cable for electrical and mechanical continuity
Confirm all earth runs connected to main grid
Labels correct/fitted
Manufacturers name plate/marker correct/fitted
Serial numbers match manufacturers test certificates
Primary connection assembly /jointing compound, no undue stress/tension on equipment, fitting bolt correctly tensioned
No dissimilar metals employed on primary connections
No rust on equipment
Site surfacing is correct and satisfactory
All fixing bolts are tight
No leaking impregnation fluid or swelling of containers
Ensure all manufacturer’s document and test certificate have been received
Operation of locking facilities
Cable entry arrangments
Ensure all equipments meet specification weather, dust and vermin proofing after installation
Examine fuses for rupturing or signs of deterioration
Switchborad testing
After all busbar joints are completed but prior to securely fitting busbar covers, measure insulation resistance of the busbars and control wiring.
Where there are any busbar joints, ductor test must be carried out prior to fitting covers. Simillar joints shall have a contact resistance within 10% of each other. The joints shall have a resistance equal or lower than an equivalent section of busbar
Test switch board earth system for electrical dan mechanical continuity. Measure earth path resistance at the earth bar to the general earth system and earth bar joints
Ensure that all protection relay have been tested accrdance with requirement of appropriate test certificate and vendor instruction
Measure insulation testing of busbar and control wiring. Test should be carrued out prior to pressure test and before energising switchboard. Minimum acceptabe test result as below. A Power frequency voltage test (pressure test) on both main and outgoing cicuits sall be carried out phases and phases to earth.
Switchgear Pre-commissioning
Following conection shall be adhered for the tests
All secondary sides of current transformers shall be short circuit
All secodary sides of voltage transformer shall be open circuit
upon completion all tests, reconnect all cables and ensure that shorting links and fuses are replace